参考答案:
根据《清单规则》计算如下:
1、地圈梁:
总长度:[(18.54-0.24)/2*2+8.34-0.24+3.0+3.3+2.7/2-0.12+3.3-0.24+3.6-0.24]*2+3.6-0.24=84.54m
工程量:84.54*0.24*0.24=4.87m~3
2、混凝土垫层:
1-1长度:[(18.54-0.24)/2*2-2.7/2+8.34-0.24-3.3+0.12+3.3+3.0+2.7/2-0.9/2+2.1+3.3-1.3*2+3.3-1.3]*2+1.5=69.24
1-1工程量:69.24*0.3*1.3=27.00
2-2长度:2*(3.3+2.7/2)+3.6-1.3=11.6
2-2工程量:11.6*0.3*0.9=3.132
3-3长度:(2.1-1.3)*2=1.6
3-3工程量:1.6*0.3*0.5=0.24
合计:26.50+3.132+0.24=30.38m~3
3、砖基础工程量:
1-1长度:[(18.54-0.24)/2*2-2.7/2+8.34-0.24-3.3+0.12+3.3+3.0+2.7/2-0.12+2.1+3.3-0.24+3.3-0.24]*2+1.5=76.74
1-1工程量:76.74*[(0.035+0.9)*0.24+30*0.125*0.0625+0.625*0.24]=46.717m~3
2-2长度:2*(3.3+2.7/2)+3.6-0.24=12.66
2-2工程量:12.66*[(1.2+0.9-0.3-0.24)*0.24+6*0.125*0.0625]=5.333m~3
3-3长度:(2.1-0.24)*2=3.72
3-3工程量:3.72*[(1.2+0.9-0.3)*0.12+2*0.125*0.0625]=0.862m~3
合计:52.912m~3
4、土方工程量:
69.24*1.2*1.3+11.6*1.2*0.9+1.6*1.2*0.5=121.50m~3